Energy | Other Energy | ISA | 18-Oct-2021 |
Existing asset | Private initiated (unsolicited) | 02-Nov-2021 |
USD 815.7 M | Design-Build-Operate, Design-Build-Maintain | 02-Nov-2021 |
South Africa / Secunda | Two Stage with preselection (shortlisting) |
Project Description
Sasol, in collaboration with Navitas, Linde and Enertrag is working on a project to produce PtL Kerosene from the Secunda Operations plant in Mpumalanga. The Secunda facility will make use of green Hydrogen that will be produced by a new, world scale electrolyser and renewable energy plants that will be built at the Secunda facility in Mpumalanga. Sasol’s existing asset base and unique, licensed technology will enable the production of green aviation fuel
Timeline
Project Definition | Project Preparation | Tender Process | Construction | Operation and Maintenance |
--
|
--
|
--
|
--
|
Project Readiness (level of completion of SOURCE’s template)
Project Documents
No documents published yet.
Project Contact
Project Assessment
5a7f9bfe-9a8d-4322-9532-150f645e1b00
South Africa
0.71
0.69
0.76
0.71
0.45
0.4
0.75
0.94
0.9
0
0
0
0
0
0
Key Country Indicators:
Source: World Bank Open Data
Energy pipeline:
Project | Capex (USD M) | Status | Subsector |
---|
204
South Africa
2
Energy
Upcoming bids
|
Pipeline Status
|
Total CAPEX (USD)
|